CHELSEA CREEK
Task
To replace and upgrade controls of BMS controllers in the apartments responsible for hot water supply, MVHR, heating & cooling of the property.
All apartments had dated controllers installed which started to fail very often and leaving residents without any controls.
Solution
EasyIO
Automation system:
Project info
1
1
1 per room
1
HWS
MVHR
Burst fires
LTHW valve
Site
Time scale
2 days per apartment
Result
Controller replaced, introduced additional thermistor in water tank for clients to be able to monitor temperature of hot water in the cylinder.
Introduced manual LTHW valve on/off function to give end user ability to close hot water supply to MVHR units during summer time.
Gave access via smart devices for full operation and monitoring of the system.
Result
Controller replaced, introduced additional thermistor in water tank for clients to be able to monitor temperature of hot water in the cylinder.
Introduced manual LTHW valve on/off function to give end user ability to close hot water supply to MVHR units during summer time.
Gave access via smart devices for full operation and monitoring of the system.